FLC Update: “Finish Work” Details
The final stages of the “finishing work” of the Family Life Center are evident as we draw closer to building being completed. Outside along the lanai and entrances, the tile is being completed and cleaned up.
Work on the FLC kitchen is moving along as the cupboards and hardware are now installed.
In the gymnasium, the dividing curtain is complete and ready for use. The basketball hoops are now in place and have been raised to keep them out of the way for the completion of the floor.
In the gymasium, within the next two to three weeks, the Teraflex flooring will be installed. When installed, it will mark a huge step towards the final completion of the Family Life Center.
On the second floor of the FLC, the final stages of the hand rails are complete.